Services provided by the Department of Electricity Request a new 3-phase electricity subscription
Details
Required documents: A copy of the applicant's ID.
Clearance.
Time required to perform it 12 days
Required fees 4050 shekels, subscription fees, 120 shekels per ampere, and the price of the prepaid meter is 700 shekels, even less than 100 amperes, and a thousand shekels above 100 amperes.
Legal Document A set of laws and regulations in Qabatiya Municipality.
Implementation procedures
Submit an application for subscription to the public service employee
Refers to the Electricity Department to find out the technical possibility of delivering the subscription according to the region
The request is referred to the Electricity Department to inspect the building to which electricity is to be delivered to make sure that it is licensed and does not have regulatory violations.
The request is referred to the Municipal Council to take a decision of approval
The request is transferred to the Electricity Department to determine the value of the materials and the contribution of the network, if any
The applicant pays the amount to the accounting and fund department
Request Documents
-
صورة عن هوية المالك أو مقدم الطلب
Service Path
-
CSC
-
electricity department
-
acquittance
-
electricity department
-
archives
CSC
electricity department
acquittance
electricity department
archives